wpeBC.jpg (2353 bytes)

OFFICE OF CHIEF CONTROLLER OF ACCOUNTS

MINISTRY OF SURFACE TRANSPORT

GOVERNMENT OF INDIA

ABOUT OFFICE    ABOUT US    CONTACT US      OTHER LINKS

Home ] Up ] Contents ] Accounts ] IA MANUAL ] Search ] Accounts at A Glance ]

 

Home ] Contents ] Accounts ] IA MANUAL ] OTHER PUBLICATIONS ] Search ] Accounts at A Glance ]

Up ] DIRECT PAYMENT ] [ IA Review 2000 ] NH Act ] Miscellaneous ] IA Review 2001 ]

 

CONTENTS

S.No                       Nomenclature                  Page Number

Part – I Introduction 4

 

Part – II Important observations of Internal Audit of CCA, MOST

  1. Summary of important Internal Audit paras/observations

Paras pertaining to :

    1. Director General ( Shipping )9
    2. Para 1 to 7

    3. Directorate of Light House and Light Ships12
    4. Para 8 to 11

    5. Chief Engineer & Administrator, Port Blair14
    6. Para 12 to 16

    7. Minor Ports Survey Organisations16
    8. Para 17

    9. General Paras16
    10. Para 18 to 22

    11. National Highway Divisions19

Para 23 to 38

Special Paras 53

Para 39 to 41

  1. Annexures

I. Statements showing State-wise status of Internal Audit Paras. 56

II. List of outstanding Internal Audit Paras of various ports wings 57 of Ministry of surface Transport.

III. List of Number of Internal Audit Paras outstanding. 58

IV. Statement showing position of outstanding Paras. 59 

V. Statement showing outstanding temporary advances 60

of DLL Chennai.

VI. Statement showing outstanding temporary advances of 61

Minor Ports Survey Organistion.

  

List of important paras/observations

    1. Director General ( Shipping )
    1. Outstanding survey fees for Rs.1,00,319/-

2. Outstanding Advance of Rs.6,56,979/-

3. Heavy amount lying in the personal deposit account

4. Non recovery of I. Tax of Rs.1,85,640/-

  1. Drawal of salary more than the sanctioned strength
  2. Payment released to Contractor without completion of work

7 Outstanding survey charges amounting to Rs.1,24,33,779/-

 

    1. Directorate of Light House and Light Ships
  1. Delayed Adjustment Of Temporary Advance
  2. Blocking Of Govt. Money Of Rs. 3.42 Lakhs

10. Payment Of Commission For Procuring The D.D. From Banks

11. Non- Recovery Of Dormitory Charges

    1. Chief Engineer & Administrator, Port Blair

12. Construction of 4 units-type-II Quarters at Hutbay

13. Delay in completion of work by the contractor entitling levy of compensations under clause 2 of the agreement.

14. In-ordinate delay in remittance of Govt. receipt

15. Delay in settlement of C.S.W.D. claims

  1. Non adjustment of huge advances under M.P.W.A.

 

D. Minor Ports Survey Organisation

17. Outstanding Advance of Rs.8,25,136/-

    1. General

18. Expenditure incurred beyond delegated powers by various units.

  1. Excess payment due to wrong pay fixation.
  2. Incurring of Capital Expenditure without Budget Provision
  3. Excess Expenditure of Rs.1,77,803/- under office expenditure
  4. Irregular/Unauthorised Expenditure
  5.  

    F. National Highway Divisions

    1. Misuse/Mis-appropriation of NH Funds
    2. Irregular/Excess purchase of Materials
    3. Un-authorised financial aid to contractor.
    4. Excess/Improper Mobilization Advances
    5. Non-adjustment of recoverable amounts from contractors and other parties placed under Miscellaneous Public Works(MPWA)
    6. Non-receipts of Materials against advance payment.
    7. Deposit work-with Railways.
    8. Fictitious adjustment of Materials.
    9. Faulty financial and contractual Accounting.
    10. Escalation charges.
    11. Loss of revenue and Mis-Classification of revenue receipts.
    12. Non- remittance of Toll collection.
    13. Mis-classification of Expenditure by NH Division.
    14. Non-adjustment/Mis-classification of hire charges.
    15. Non-Maintenance/Improper maintenance and non-productions of records.
    16. Mis-appropriation of funds/Materials
    17.  

      Special Paras

    18. Use of Inferior type of Material at Zira-Talwandi-Faridkot Road KM/185-05 to 223-75.
    19. Whereabouts of 276 Govt. Machineries are not known.

        S. Construction of drainage to avoid recurring expenditure-Suggestion of IAP

 

 

PART – I

Intorduction

  1. Duties entrusted to the Internal Audit

The Internal Audit Wing of this office conducts audit of the offices under the administrative control of the Ministry of Surface Transport in accordance with the provisions of Civil Accounts Manual.

The duties of the Internal Audit are to ensure that initial records are maintained properly, uniform procedure is adopted in the matter of payments and accounting and corrective measures are adopted wherever necessary in order to bring the improvement in accounting. Summarily, the main duty of the internal audit wing is to examine if the Ministry and its subordinates offices are functioning in accordance with the relevant Govt. Rules and exchequer are under safe control.

Out of 65 units ( excluding bank audit ) which were due for audit during 1999-2000, 53 units could be audited due to paucity of time, manpower and weather constraint ( for Andaman & Lakshadweep Islands ). As regards bank audit 4 banks have been audited during 1999-2000.

In addition to above the Ministry of Surface Transport has also been entrusted the work of construction and maintenance of National Highways to the PWD NH Division of state/UT Governments on agency basis. There are 317 divisions(Approximately, as this number keeps changing) all over India under the Accounting Jurisdiction of Seven Regional Pay & Accounts Offices and Pay & Accounts Office (NH) Head Quarters of Ministry of Surface Transport. The Regional Pay & Accounts Offices and Pay & Accounts Office (NH) are functioning under the administrative control of Chief Controller of Accounts, Ministry of Surface Transport. The audit of state PWD Divisions is conducted by the RPAOs in respect of NH Accounts.

The object of Internal Audit is to ensure that high standard of Public financial morality and sound financial administration and devotion to the financial interest of the Government is maintained in the Divisions entrusted with NH work. The periodicity of Internal Audit in general is based on the size of establishment/ scheme/project being audited, budget allotment etc.

 

II ORGANISTAIONS AUDITED

Organisations audited during the year may be classified under following categories:

  1. Directorate of Shipping
  2. Directorate of Light House & Light Ships
  3. Chief Engineer and Administrator, ALHW, Port Blair
  4. Minor Ports Survey Organisation
  5. National Highway Divisions

 

 

III TARGETS AND ACHIEVEMENTS DURING 1999-2000

Total 317 Public Works Units dealing with National Highway works in the States/UTs, 65 units pertaining to various wings of the Ministry (other than NH) and 17 bank branches fall under the purview of Internal Audit. Ideally these units are to be audited every year, but due to the reasons explained below all the units could not be audited during 1999-2000. 82 Public Works Divisions for National Highway work have been inspected and a total of 745 paras are raised during this year. There were 5970 outstanding at the beginning of this year. Out of 5970 paras, 556 have been settled. 65 units pertaining to other wings of the Ministry (other than NH) have been audited during 1999-2000. 418 out of 1442 old Internal Audit paras of other wings of MOST (other than NH Divisions) have been settled during the year of report. Internal Audit of the bank branches has been undertaken recently and during this year 4 bank branches have been audited. Special audit of Sub-marine pipeline project under Mumbai Port Trust was also conducted during the year under review.

 

IV Arrears, if any and steps taken to clear the same

As a result of concerted and rigorous efforts of audit parties, who have been specifically advised to attend to old outstanding paras 418 old paras out of 1442 old paras have been settled along with raising a substantial number of new paras i.e.404 during 1999-2000.

 

As regards the audit of NH divisions of state PWD, RPAOs are asked to inspect one or two units every month as per directions of CCA, MOST. Yet time bound work viz. reimbursement of monthly claims, timely submission of accounts and other work allotted by CCA are the main responsibilities of RPAOs, hence Internal Audit is difficult to extend further. The other reason for arrears at RPAOs level is due to shortage of staff and availability of funds under Travel Expenses. There is only one JAO/AAO posted in each RPAO who has been assigned with the duties of supervising the pre-check of vouchers received with the reimbursement claims of AGs as well as of DDOs, compilation of monthly accounts, monthly/quarterly reports and returns sent to CCA office alongwith the additional work of conducting audit of different units scattered all over in the assigned states. The shortage of staff directly effects the quantity and quality of Audit. Inspite of above hindrances, efforts are being made to bring down the arrears. It is needless to mention that RPAOs should be strengthened by providing more staff for effective control over the expenditure on NH Works incurred by the state PWD.

 

V General Conditions of maintenance of Internal Accounts Records

  1. Office under the Control of the MOST (other than NH Divisions)

Although there is improvement in the general condition of maintenance of internal accounts records, there is still a lot of scope for betterment. Distinct improvement noticed as a result of internal audit is mentioned below :-

    1. Improvement in maintenance of records :-
      1. After having been pointed out by the audit, the dead stock register are being reviewed. Physical verification of stocks has been carried out and unusable stocks have been removed from the stock registers for further necessary action to dispose off.
      2. Many units took necessary action to dispose off the unusable material after approval of survey reports by the competent authority.
      3. Maintenance of cash book has improved. Cutting /over writing and erasing is very less now and necessary certificates are being recorded by the DDOs besides checking the cash books regularly.
    1. In case of D.G.(LHLS) it had been observed during various inspections that they were observing partially, CPWD rules and partially their own set of orders. It has been advised to evolve a detailed set of accounting and financial rules after incorporating/adopting CPWD rules etc.
    2. The bank audit which has been taken up during the year 1999-2000 has revealed that the payment of D.A. to the pensioners was not being paid on the original pension, but on the reduced amount i.e. the amount arrived at after deducting the amount allowed for commutation. The same had been got corrected. And also the pension which needs to be enhanced after 15 years from the date of commutation was got done in several cases and with instruction to follow the correct procedure in future.
  1. National Highway Divisions

From the review of different audit reports it is transpired that there is little improvement in maintenance of records of accounts in NH Divisions. However, observation conveyed through the reports reveals that omission involving heavy financial implications is increasing rapidly. It is also pointed out that some Division did not produce the relevant records so as to avoid adverse comments from audit. It is also noticed that some Divisions are not maintaining the records or maintaining the records improperly. It was also pointed out earlier in the previous Annual Review. The same practice is continuing. For better result, it is suggested that the staff of NH Division of state PWD may suitably be instructed/trained for proper maintenance of Accounts records and observance of relevant rules and regulations as provided in General Financial Rules, Delegation of Financial powers, Central Treasury Rules and Receipts and Payment rules. This will save a considerable time, efforts and amount of Government. It is pertinent to mention that none of the PWD divisions furnish compliance report to audit. Matter was taken up with Director General-Road, CEs of state PWDs and PWD secretaries of respective state Government but things have not improved. It is high time to find out some remedy to this problem of non-observance of instructions by state PWDs.

 

VI Details of Schematic review and audit of Public Sector Undertakings

    1. We are not auditing the accounts of PSUs nor reviewing their schemes. Special audit is conducted at the request of Ministry. Special audit of sub-marine pipeline of Mumbai Port trust was conducted by this office and report was submitted to Ports Wing.
    2. The audit of Public Sector Bank, the accredited Bank of the Ministry of Surface Transport, i.e. Syndicate bank associated with the day to day working of the various units of the Ministry located all over India has also been taken up as per directives and guidelines given by C.G.A. The audit of three banks has already been completed during 1999-2000.

 

VII Whether any merged DDO system is working under the Ministry and

if so how is its performance :-

The scheme of the merged DDO was introduced in this Ministry since April 1986 only in respect of two DDOs of Secretariat. There is a need felt to review the administrative and reporting channel of DDOs. Further improvement is required in the fields like maintenance of GPF records, contingent expenditure record, budget monitoring, use of appropriate forms for drawal of money etc.

 

VIII Suggestions, if any, made by Internal Audit leading to economy in expenditure or Recovery of over payment.

While conducting audit of various units, suggestions were made in the form of audit paras regarding economy in expenditure or recovery of over payment . A detailed coverage is made in respect of important paras in Part-II of this report.

 

 

PART – II

 

SERIOUS IRREGULARITIES OVER PAYMENTS NON-MAINTENANCE OF RECORDS/ACCOUNTS AND OTHER IMPORTANT SHORTCOMINGS OBSERVED IN INTERNAL TEST CHECK DURING THE YEAR 1999-2000.

 

 

DIRECTOR GENERAL ( SHIPPING )

Para 1 - Outstanding Survey Fees for Rs. 1,00,319/-

The Surveyor-in-charge, Cochin carries out the following functions:-

  1. Statutory survey of safety equipment and load time ships.
  2. Undertakes safety radio telegraph survey.
  3. Registration of sailing vessels conduct annual inspection and issue of free board certificate and inspection certificate.
  4. Carrying out shipping master’s duties such as engagement and discharge of officers and crew of ships etc.

Under the provision of Merchant Shipping(Sailing Vessels) Act, 1977, the surveyor-in-charge should collect the various kind of fee from the owner of the ship, a certificate to this effect should issue to the owner of sailing vessels after conducting survey.

It was observed that an amount of Rs 1,00,319/- on accounts of various kind of survey fee was outstanding against the owner of sailing vessels. The amount needs to be realised from the concerned parties at the earliest.

[Para 3 of F.No. IA/SFT/6(35)/98-99]

 

 

Para 2 - Outstanding Advance of Rs.6,56,979/-

The unit is paying temporary advances to the concerned officer/staff to meet the day to day works expenditure. Several items totaling Rs.6,56,979 pertaining to the period 1982 to 1999 are still lying outstanding for want of adjustment bills from the staff of DLL Port Blair. This may be got cleared at the earliest under intimation to audit.

[Para 1 of F.No. IA/SFT/4(5)/98-99]

 

Para 3 - Heavy amount lying in the personal deposit account

Personal deposit account is an arrangement intended to facilitate the office to credit receipts into and effect withdrawals directly from the account subject to an over all check being exercised by the Bank in which the account is authorised to be opened to ensure ( with the help of personal ledger account to be maintained by the Bank for the purpose) no over withdrawal . The account has to be maintained properly and utilised for the purpose for which the account is opened.

The office of Shipping Master, Mumbai is maintaining the personal ledger account namely PLA-I and PLA-II. In case of Account No. PLA-I, it has been found that the credits are being received from the agencies of the concerned ships on account of undisbursed Pay & Allowances of crew employees. In case of absconding crew members, the agency deposits undisbursed Pay & Allowance to the office of Shipping Master, Mumbai, who in turn remits such money to the families of such crew members.

The audit party has found a credit balance of Rs.37,24,988/- as on 31.3.99, whereas there was no details of persons to whom this money to be charged. The credits are piling up year by year, in this account. In spite of this fact having been pointed out by audit party, nothing has been done to make out a list of the claimants or the address of their families where amount are to be sent.

The same office i.e. Shipping Master, Mumbai is maintaining another personal ledger account – PLA-II for crediting money received as advance from Shipping agencies on the request of employees working under them for sending the same to their families.

The audit party found a credit balance of Rs.47,18,263.90 as on 31.3.99. This amount should have been sent to the families of those crew members whom their employer agencies had sent. The office of Shipping could not even produce a list of crew members to whom the money belonged.

[Para 6 & 7 of F.No. IA/SFT/6(16)/98-99]

 

Para 4 - Non recovery of I. Tax of Rs.1,85,640/-

As per provision contained in section 194- C of I. Tax Act, 1961 (43 of 1961) the Income Tax should be deducted @ 2% before making payment to contractor. During course of inspection of D.G. (Shipping) Mumbai, it was seen that payment amounting to Rs.92,82,000 were released to contractor, without deducting the income tax @ 2% . Rs.1,85,640 the recovery should have been effected before payments to contractor to avoid huge loss to Govt. revenue. The matter needs to be investigated further and remedial action may be taken by office of DG Shipping.

[Para 1 of F.No. IA/SFT/6(26)/98-99]

 

Para 5 - Drawal of salary for more than the sanctioned strength

In the office of D.G. Shipping Mumbai, the salaries of 4 Executive Officer have been drawn against the sanctioned strength of 3 executive officers. Also the salaries of 4 nautical officers have been drawn against the sanctioned strength of 2 nautical officer. It is advised that excess posts in both the cadres should either be got sanctioned by the competent authority or alternatively the person posted should be reverted.

[Para 9 of F.No. IA/SFT/6(26)/98-99]

 

Para 6 - Payment released to Contractor without completion of work

 

Normally the payment to executing agency of the work awarded should be finally released on the completion of work as has been clearly stated in rule 137 of Receipt & Payments Rules. From the scrutiny of records, it has been revealed that a sum of Rs.17,87,400/- was released by D.G. ( Shipping ) Bombay to the contractor without completion of the job. Such instances does not entail misuse of Govt. money only, but also violate the laid down procedures. Such trend need to be arrested and D.G. ( Sh.), may give reason of non compliance of rule/provisions.

[Para 2 of F.No. IA/SFT/6(26)/98-99]

 

Para 7 - Outstanding survey charges amounting to Rs.1,24,33,779/-

The unit is rendering services of survey of Minor Ports and for that survey charges are claimed from the concerned Deptt. It was observed that a sum of Rs.1,24,33,779/- due from various parties on this account is still lying non-settled. The details of unit form whom the survey changes are due are as follows

S.No. Name of the agency Amount outstanding

---------------------------------------------------------------------------------------------

1. I.W.A.I. W.C.C. 10, 19, 903, ]

Brahamputra 35, 56, 300 ]

 

2. V.I.T. Lakshadweep 15, 60, 000

3. C.P.T. 1, 42, 880

4. W.H.P. – C.O.S. 20,89,686

5. K.P.T. 40,65,050

-----------------------------------------

1,24,33,779

-----------------------------------------

Urgent action is required to get the outstanding survey charges settled.

[Para 5 of F.No. IA/SFT/6(1)/98-99]

 

 

DIRECTOR GENERAL ( LHLS )

 

 

Para 8 - Delayed adjustment of temporary advance

On scrutiny of records of DLL Chennai it was seen that temporary advances amounting to Rs.1,02,116/- as per Annexure-V consisting of capital and revenue advances pertaining to the period as old as February/March, 1996 have been either adjusted late or still eluding adjustment. This trend which is prevailing in the office need to be streamlined and temporary advances whether capital or revenue should be adjusted without further delay.

[Para 4 of F.No. IA/SFT/4(12)/98-99]

 

Para 9 -Blocking Of Govt. Money Of Rs. 3.42 Lakhs

A jeep for official use was purchased at a cost of Rs. 3,42,206/- lakhs in May, 1998 by DLL Jamnagar. The vehicle was got insured in 6/98. Since then the vehicle is lying in the garage and not being used at all. The vehicle has not been used for such a long period, the purchase of vehicle does not seem to be prudent and amounts to blocking of Govt. money to the tune of Rs.3,42,206/-. A due care need to be taken to avoid recurring of such lapses in future and vehicle needs to be sent to office/department which may use it productively.

[Para 3 of F.No. IA/SFT/4(3)/98-99]

 

 

Para 10 - Payment of commission for procuring the D.D. from Banks

It was observed that Director Light House & Light Ships Jamnagar had not been procuring DD’s from its accredited bank i.e. Syndicate Bank. During 1998-99 an amount of Rs.42,000/- was paid as commission charges to Syndicate Bank. As per instructions of R.B.I. the accredited bank has to procure DD’s free of cost for the DDOs. The said instructions may be followed strictly to avoid infructuous expenditure.

[Para 7 of F.No. IA/SFT/4(3)/98-99]

 

Para 11 - Non- recovery of Dormitory Charges

The Inspection party observed that Director, Training Center Calcutta have been imparting training to the technician’s and Light Keeper of various offices under the D.G. ( LHLS ) and no dormitory charges are being recovered from the trainees as they are being provided accommodation duly furnished with cots wedding and mosquito nets etc. The training center is required to change Rs.2.25 per day per trainee, During the past 5 years, position of trainee imparted by Training Center is as under :-

Period of Training No. of Trainee

------------------------------------------------------------------

18.4.94 to 15.7.94 15

5.9.94 to 16.9.94 6

15.4.95 to 29.5.95 9

28.8.95 to 28.11.95 15

13.5.96 to 28.6.96 8

15.4.97 to 23.5.97 7

3.2.98 to 18.3.98 6

18.1.99 to 16.3.99 6

------------------------------------------------------------------

Total amount computed on the basis of, above table comes to Rs.4500/- approx. which need to be adjusted immediately.

[Para 2 of F.No. IA/SFT/4(10)/98-99]

 

 

CHIEF ENGR. & ADMINISTRATOR, PORT BLAIR

Para 12 - Construction of 4 units-type-II Quarters at Hutbay

During inspection of EE(C), Hutbay it was observed by the Inspection Party that the department had done numerous irregularities in a construction of above units namely viz.

1. M/s K. Parmeswaran who quoted an amount of Rs. 6,11,814/- i.e. 7.33% above the estimated cost of Rs.5,70,009 which was higher in comparison to other competitors. Apart from this there were other irregularities such as:

  1. Irregular payment to contractor without obtaining completion certificate from the SE.
  2. Non-conducting of Test Check by the Ex. Engineer and the Asstt. Engineer.
  3. Non-employment of Engineer by the contractor being a specific clause of the contract.
  4. Non-preparation of work abstract as per para 10.5.25 of CPWA Code.
  5. Escalation of Rs.16,000/- granted without any hindrance which normally should be dealt as per provision of para 3.3.5 of CPWD Manual.
  6. Delay in completion of work by the contractor entitling levy of compensation under clause 2 of the agreement at the rate of 10% of the estimated cost of Rs.5,70,009/- which comes to Rs. 57,009/- need to be recovered from the contractor.

[Para 3 of F.No. IA/SFT/5(1)/97-98]

 

Para 13 - Delay in completion of work by the contractor entitling levy of compensations under clause 2 of the agreement.

 

A contract was awarded by Ex. Engg. Campbell Bay for Rs.3,24,651 for construction of 4 units of type ‘A’ Qrs. at Kamorata as per agreement No.36/96-97. The Rs.8,25,136/- pertaining to the period 1997-98 are still lying outstanding for want of adjustment. The stipulated date of completion of work was 24.11.96. As the contractor failed to abide by the time schedule, it was mandatory on the part of the Ex. Engr. To levy 10% of the estimated cost of contract which works out to Rs.32,465/-

[Para 5 of F.No. IA/SFT/5(4)/97-98]

 

Para 14 - In-ordinate delay in remittance of Govt. receipt

The rule 3 of G.F.R. stipulates that on money received by or on behalf of Govt. either as dues of Govt. or for deposit, remittance or otherwise should be brought into Govt. Account without delay as also envisaged in para 1.17.1 of Civil Accounts Manual. During inspection of 96-97 & 97-98 of E.E. ( Campbell Bay ), it was noticed that drafts/cheques were remitted to bank after a lapse of 15 days to 2 months. For example, three cheques bearing No. 590746 dated 24.4.96, 594165 dt.21.3.96 and 594168 dt.31.3.96 for Rs.1,45,402/-, Rs.1,37,126/- and Rs.1,00,000/- respectively, they were deposited into Govt. Account after 15 days or more than 15 days. This trend of blocking Govt. money needs to be checked immediately.

[Para 4 of F.No. IA/SFT/5(4)/97-98]

 

Para 15 - Delay in settlement of C.S.W.D. claims

As per codal provision each claim is required to be verified/adjusted, within 10 days of the receipt. During scrutiny of register ( claims ) received from the o/o the Ex. Engg.( CSWD), Port Blair, it was observed that the above provision was not adhered to by the Division resulting in 14 items amounting to Rs.70,15,864/- relating to the period 6/96 to 12/97 were lying outstanding for want of adjustment till April,99. Prompt action need to be initiated in the matter.

[Para 7 of F.No. IA/SFT/5(11)/98-99]

 

Para 16 - Non adjustment of huge advances under M.P.W.A.

A scrutiny of M.P.W.A. ( Miscellaneous Public Works Advances ) Register of Dy. Chief Engg. ( Dry Dock, Port Blair ) revealed that a sum of Rs.3,12,009 was outstanding under this head. Out of which an amount of Rs.1,60,456/- and Rs.1,23,058/- pertain to the period 1981-82 to 1997-98. Since the amount involved is substantial and mostly given to parties an advance payment of the material a very prompt & strict action require to be taken either to procure material or adjust the amount.

[Para 4 of F.No. IA/SFT/5(8)/98-99]

 

MINOR PORTS SURVEY ORGANISATION

Para 17 - Outstanding Advance of Rs.8,25,136/-

The unit is paying temporary advances to the concerned officer/staff to meet the day to day works expenditure. It was observed from the record that an amount of Rs.8,25,136/- pertaining to the period 1997-98 as per Annexure-III are still lying outstanding for want of adjustment.

[Para 2 of F.No. IA/SFT/6(1)/98-99]

 

GENERAL

Para 18 - Expenditure incurred beyond delegated powers by various units

As per delegation of financial power Rules, Head of office is empowered to incur expenditure upto Rs.4,000 per annum on purchase of Stationery items during a year and Head of the Department can incur expenditure of Rs. 40,000/- per annum. Contrary to said Financial Power Rules, the following units have incurred expenditure on purchase of stationery items more than the financial powers.

 

 

S.No. Name of the Unit Year Total Expenditure

1. DLL (Training), Calcutta 1998-99 5,802/-

2. DLL Cochin - do - 5,759/-

3. Shipping Master, Mumbai - do - 35,968/-

4. Shipping Master, Calcutta - do - 25,728/-

 

The irregular expenditure needs to be got regularised from the Head of the Department/- Finance Wing of the M/o Surface Transport.

 

Para 19 -Excess payment due to wrong pay fixation

i) During inspection of D.G. ( Sh.), Mumbai, it was observed that wrong fixation of Pay of Sh. K.P. Jason, U.D.C. during 1.1.88 to 18.9.91 an excess amount of Rs.20,775/- on accounts of Basic Pay was paid by D.G. ( Sh. ) Mumbai away from the allowance paid thereon. The amount is substantial & need to be recovered & adjusted in Govt. account immediately.

ii) The inspection party on scrutiny of service book of Sh. R.M. Kalingam, Dy. Director and R.K. Varadaraj observed that W.E.F. 1.1.96 to 30.9.96, the pay of the officers was wrongly fixed thus making an extra payment amounting to Rs.1,66,291 to the above officials. Since the amount involved is substantial, same needs immediate action to recover.

[Para 8 of F.No. IA/SFT/6(26)/98-99]

 

Para 20 - Incurring of Capital Expenditure without Budget Provision

Under the provision of Rule 6 of GFR, the expenditure should not be incurred on the work without budget provision. During inspection of DG(Sh.), it was noticed that capital expenditure on the supply and installation of vertical blinds and false ceiling was incurred without allocation of fund. This work was not related with any sanction. As such, entire expenditure of Rs.12,47,400/- is irregular and should be got regularised from the Ministry of Finance.

[Para 5 of F.No. IA/SFT/6(26)/98-99]

 

Para 21 - Excess Expenditure of Rs.1,77,803/- under office expenditure

During the course of inspection of MMD, Chennai, it was observed that an excess expenditure to the tune of Rs.1,77,803/- has been incurred over and above the Budget allotment which was Rs.6,21,000/- and expenditure incurred Rs.7,98,803/- during the year 1998-99. The Deptt. did not initiate any action to get it regularised from the competent authority. Urgent steps need to be taken to get the excess amount regularise from the competent authority.

[Para 11 of F.No. IA/SFT/6(34)/98-99]

 

Para 22 - Irregular/Unauthorised Expenditure

During inspection, it was observed that paint purchased amounting to Rs. 27,594/- were purchased without the sanction of the competent authority. The Director who is not empowered to make such bulk purchases require to get the expenditure regularised by obtaining the ex-post-facto sanction of the Head of the Department.

[Para 4 of F.No. IA/SFT/4(11)/98-99]

 

 

NATIONAL HIGHWAY DIVISIONS OF STATE PWDs

Para 23(a)- Misuse/ Mis-appropriation of NH funds amounting to Rs. 331.44 lacs

Expenditure should not be incurred on any new item of work without prior approval of the competent authority subject to availability of Funds as per Universal cardinal and principles of accounting and financial regulations. Any transaction done against the provisions of proper sanction would be categorised as misappropriation of Funds with the intention of merely utilising the unspent funds. It has been observed during the Inspection of NH Divisions that NH Divisions are incurring expenditure from NH Funds on civil works of states such as construction and maintenance of office Buildings, residential quarters, constructions of boundary walls, godowns, sheds & houses, electric switches etc or funds are transferred to Deposit/ MPWA and kept accumulated thereof. Such expenditure is being charged to NH works in contravention of Financial propriety. Audit has noticed such instances during inspection in 1999-2000 which amounts to Rs. 331.44 lacs.

A gist of few paras are being given below:

    1. During scrutiny of the records of NH Division Guwahati it has been pointed out by the Internal Audit that an amount of Rs. 3,31,44,540 was drawn against hand receipt bills and booked the expenditure to the final heads of Accounts of the Ministry of Surface Transport as per details below
    2. Year

      Head of A/c

      Amount drawn against hand receipt

      93-94

      5054

      8,73,641

      93-94

      3054

      13,01,000

      94-95

      5054

      3,00,00,000

      95-96

      5054

      5,94,949

      95-96

      3054

      2,94,950

      3,31,44,540

       

      It could not be immediately ascertained in audit whether the withdrawn funds were utilised on specific works/profects from which it was withdrawn. However it is seen that out of Rs. 3,00,00,000 kept in revenue deposit in 3/95, Rs. 2,45,00,000 were drawn in favour of 13(thirteen) Nos. of NH divisions and the Bank Draft for Rs. 245 lakhs were forwarded to the Deputy Secretary to the Govt. of Assam, PW(Budget) department vide Executive Engineer’s letter No. A-III/94-95/3723 dated 10.7.95. The balance amount was drawn and utilised by the division during 7.95 and 8.95. This indicates that funds provided in the budget for specific purposes were diverted for other use. An amount of Rs. 76,30,000 was transferred to the revenue deposit Head in 6.98 by debiting NH works, under MH-5054 and the amount was spent in 8.98 by adopting similar method. The Cheque for Rs 3.00 crores was issued in favour of Secretary PWD Assam. Out of Rs. 3.00 crores, an amount to the tune of Rs. 2.45 crores was distributed among 13 Divisions in the subsequent year for utilising the amount against NH works. Drawal of money by transfer to a deposit head to avoid/lapse budget provisions is prohibited under the financial rules.

      (Para-3 of report No.41)

      Para-23(b) Incorrect booking of various expenditure to NH Works amounting to Rs 23.75 lacs

      In 1984 Ministry of Surface Transport issued instructions vide their letter nos. NH/11/P/1684 dated 28.01.84 and No. RW/NH-III/8/81 dated 16.2.1984 that expenditure on salaries of supervisory staff, repair of Jeep car and POL, purchase of stationery, payment of telephone bills and other office contingencies etc. must not be charged to NH Works as the Ministry of Surface Transport is paying 9% Agency changes to state Government. During test check of records of the NH Divisions, it has been observed that an expenditure of Rs. 23.75 lacs has been incurred on such items which is contrary to the provisions and orders of the Ministry of Surface Transport.

      A few examples are given below:

    3. Test check of records of CW Division-III Ludhiana revealed that an expenditure of Rs. 1.71 lacs on POL, repair of Jeeps, purchase of stationery, telephone charges has been charged to NH Works. The amount is to be met out of State Budget in lieu of 9% agency charges paid by the Central Government. This irregular expenditure requires to be withdrawn from NH Works.
    4. (Para 8 of report No. 13)

    5. Similarly on verification of records of CW Division Ferozpur, it is seen that expenditure amounting to Rs. 81796/- has been booked to NH Works on account of Pay of work Munshi. Being a supervisory staff the pay of work Munshi was to be charged to state head of account as per instructions issued by the Ministry of Surface Transport. As such this irregular expenditure may be withdrawn form NH accounts.
    6. (Para 4 of report No. 40)

    7. During test check of records of NH Division Rohtak, it is noticed that an amount of Rs. 1.01 lacs spent against POL purchase of stationery & advertisement have been claimed out of the NH Work estimates which is irregular. All such irregular/un-authorised expenditure may be withdrawn from NH work.

(Para 12 of report No. 59)

 

 

 Para 24 Irregular/Excess purchases of Materials – loss to MOST (amounting to Rs. 38.94 lacs)

In terms of Accounting procedure of PWD, it is desirable to retain the supply of materials to contractors in the hands of Government provided that a clause to this affect has been inserted in the terms and conditions of contract. Material issued to the contractor under such clause should be intended for the use and consumption on the specific work. Materials should not be issued to contractor in bulk in advance long before their actual requirements as to avoid inherent risk of pilferage and misuse. But during inspections of NH divisions it was noticed that materials were purchased without any provision or purchased in excess of actual requirement. Audit has pointed out such irregularities in 8 paras amounting to Rs 38.94 lacs.

A few such instances are given below:

24.1 On scrutiny of records of Temporary Division Construction Unit (NH) Lucknow, it is observed that an excess Expenditure of Rs. 6,28,535/- (cost of Excess bitumen 81.9 MT used) has been incurred by use of Excess bitumen on Job No. 148 as per detailed below

 

Vr. No.

Cash Book no.

KM

Required

Used

Excess

102/17.3.97

2/AB IV/96-97

43

15.05

16.8

1.75 MT

103/17.3.97

4/AB IV/96-97

46

15.05

16.8

1.75 MT

106/17.3.97

------

39

15.05

16.94

1.89 MT

107/17.3.97

------

54

15.05

16.8

1.75 MT

314/30.3.98

1/SE/97-98

109

54.6

91

36.4 MT

Thus 81.9 MT (45.5 MT (26 X 1.75) + 36.4) excess bitumen has been used in M.S.S. work in 26 KMs cost of which works out ot Rs. 6,28,535(81.9 X 76.50).

(Para 7 of report No. 29)

    1. On verification of MPSS register of NH Division Cuttack it has been observed that accounts cleared upto 3/99 and that a balance to the tune of Rs. 75,53,638 was lying unadjusted since long in Material Purchase settlement suspense accounts Division was advised to take necessary steps to reconcile the accounts with reference to stock account and payment made.
    2. (Para 8 of report No. 61)

    3. On scrutiny of records of NH Division-II Midnapore, it was observed that 421.55 MT of bulk Bitumen were purchased upto 3/99 against Job No. 006-WB-97-123 and 91% of the Job was completed by the Contractor upto 4th R.A. Bill after consuming 217.207 MT of Bitumen. The 5th & final RA Bill pending with the Division has not been submitted to Audit. It is realised that the balance of bulk bitumen i.e. 204.343(421.55.217.207) was not required to complete the Job but the cost of Bitumen was booked against this particular job.

(Para 1(C) of report No. 69)

 

 

 

Para25 Un-authorised financial aid to contractors amounting to Rs. 4408.19 lacs.

Provisions do exist in the agreement for enforcement of timely completion of works. Job work is required to be completed within the stipulated period as per conditions of contract. In case work is not completed by the contractor within the stipulated period of time as provided in the contract, the executing authority has the right to impose penalty or rescind the contract at the risk and cost of the contractor. In the course of scrutiny of records of some NH Divisions by ITC, it has been revealed that the works were not completed within stipulated period specified in the contract and even no extension of time for completion of the work was granted to keep the contract alive. No penalty was levied for delay in execution of work by contractor.

Hence Non-recovery of penalty, Non-levy of compensation for delay in completion of work by the contractor, non-recovery of excess expenditure from defaulting contractor for abandonment of work and its executions from other contractor at the risk and cost of initial contractors constitute un-authorised financial aid to contractors. During the course of Inspection, it has been noticed that monetory loss to the MOST amounts to Rs4408.19 lacs on this account during 1999-2000.

 

Some important paras involving financial implications are noted below :-

    1. During verification of records of NH Division Udaipur(Rajasthan) it has been observed that work "construction of remaining work of Udaipur By Pass (Phase I) KM 0/0 to KM 5/718(0 at KM 263/505) of Ajmer Udaipur Road on NH 8" (Jo No. 008/RJ/95/148) was awarded to M/S Shiv Construction Co. Udaipur with the stipulated date of completion of 3.9.97. The contractor had failed to maintain the prorata progress of the work and the contract was rescinded by Addl. Secy., Govt. of Rajasthan on 19.3.97. Therefore the contractor was imposed compensation @ 1% amounting to Rs. 29,47,391 out of which Rs. 18,52,701/- was recovered. Balance amount of Rs.10,94,690/- is outstanding against the contractor. The balance amount of compensation of Rs. 10,93,690/- has not so far been recovered from the contractor. This tantamounts to un-authorised financial aid to the contractor.
    2. (Para 1(1) of report No. 2)

    3. Job No. OD1-PB-86-028-widening to 4-lane Delhi-Amritsar Road-NH-I Section Sirhind to Jalandhar in Punjab, Road Works Package from 294-835 to KM 320.475 contract No. IV
    4. As per terms of agreement in the records of CW Division-I Ludhiana, the work was to be completed within 42 months i.e., upto 27.2.90 but the work was in progress upto 3/99. As per agreement clause liquidated damages at 10% of the estimated cost was to be imposed upon the contractor as penalty which works to Rs. 131.39 lacs. No penalty has been levied against the contractor. As such the contractor has been favoured.

      (Para 1(F) of report No. 52)

    5. On scrutiny of Accounts records of CW Division –I Ludhiana it is seen that the work given to the contractor was not completed within the stipulated period. No records are available to support the extension being given to contractor. As per the records this contract is no longer valid. No action to levy compensation in terms of Clause – 2 of the agreement was initiated by the Division which tantamounts to undue financial aid to the contractor to tune of Rs. 14,41,556/-
    6. (Para 6 of report 52)

    7. Scrutiny of accounts record of World Bank Project Division PW(B&R) Ambala Cantt. revealed that the work given to the contractor was not completed within the stipulated period. No action was initiated by the Division to levy compensation in terms of clause – 47.1 of agreement which tantamounts to undue financial aid to the contractor to the tune of Rs. 3354.60 lacs limited to 10% of total cost which works out to Rs. 2449.20 lacs.
    8. (Para 3 of report No. 60)

    9. Similarly in the case of ADB-II Palwal, work was to be completed within 48 months i.e., 4.4.1995. Time extension was granted thrice upto 31.12.99. But work is still in progress. Non-recovery of the liquidated damages shows undue favour to the contractor resulting in loss for Rs. 298 lacs to the Ministry of Surface Transport.

(Para 1(b) of report No. 77)

 

  

Para 26 Excess/Improper Mobilization Advance amounting to Rs 474 lacs.

In terms of rules laid down in CPWD manual Vol-II Mobilization advance, subject to a maximum limit of 10% of estimated cost, are sanctioned to the contractors as advance on the security of Machinery and plants brought to site for specialised and capital intensive works costing not less than Rs. Two Crores which is further subjected to 80 % of the cost of machineries and plants to brought to the site. During the course of inspection of NH Divisions, it has been noticed that set norms for sanction of such advance are not being followed strictly while issuing sanctions for grant of Mobilization Advance. Audit has observed that instances are there where Mobilization Advance was given in excess of the admissible limits and interest thereon is not being charged as no clause for levy of interest has found to be incorporated in the contract. A few cases of recovery of Mobilization Advance is still pending although the work has finally been completed. It has also been noticed that interest on Mobilization advance though recovered but taken as state receipt by NH Divisions. The balance amount of mobilization advance should have been adjusted from the final Running Account of the contractor. The Divisions have not discharged their duties properly.

 

Some of important cases are given below:

    1. On verification of records of Provl. Division-II W.B. Panipat, it is noticed that M/S CCC Ltd. who was awarded the work has since been expelled from the work in 5/96. But Mobilization advances of Rs. 143.82 lacs is still outstanding against the contractor. Amount is required to be recovered and credited to Govt. of India accounts.
    2. (Para 4 of report 35)

    3. Similarly, a Mobilization advance of Rs. 94.39 lacs was given to M/S NBCC by Provl. Division-II WB Panipat. The contractor was expelled from the work in 10/92 and the work has since been realloted to an other agency. An amount of Rs 70.79 lacs of outstanding Mobilization advance along with interest thereon has not been recovered/adjusted against machinery hypothecated.
    4. (Para 5 of report no. 35)

    5. Scrutiny of records of Express way Division – III Vadodra reveals that additional Mobilization advance of Rs. 255 lacs was paid to the contractor inspite of unsatisfactory progress of the work and contrary to contractual conditions in addition to initial Mobilization advance of Rs. 259 lacs i.e. 10% of contract amount as per clause 60 of agreement. This is an improper payment made to the contractor.

(Para 3 of report No. 72)

 

 

Para 27:Non adjustment of recoverable amounts from contractors and other parties placed under Miscellaneous Public Works Advances(MPWA) amounting to Rs 112 lacs.

In terms of codal provisions laid down in the systems of Public Works Accounts, no amount should be debited to "MPWA" for want of sanctions or appropriations . But during inspection of NH Divisions it has been observed that instead of effecting recovery, dues have been debited to MPWA. Audit has reported that a sum of Rs. 112 lacs against 6 paras is outstanding under MPWA. Divisional authorities did not initiate any tangible action to liquidate the outstanding balance under MPWA.

Some illustrations are given below:

    1. On scrutiny of MPW Advance Register of NH Division Kurnoul it is seen that an amount of Rs. 71.74 lacs has been outstanding since 3/97 towards the cost of Bitumen to M/S Indian Oil Corp. Ltd & M/S Bharath Petrol Corp. Ltd. Neither the materials were supplied to the full quantity nor the amount refunded by the company for a long time.
    2. (Para 4 of Report No. 18)

    3. From a review of MPWA Register of NH Division Bijapur, it is noticed that an amount of Rs. 9.74 lacs is outstanding since 4/98 towards the cost of Asphalt, cement & workmen compensation. They have neither supplied the material nor refunded the amount outstanding.
    4. (Para 5 (Part III) of report No. 31)

    5. During scrutiny of records of NH Division Cuttack it was observed that an amount of Rs. 52.16 lacs was outstanding balance in MPWA Register as on 31.3.99. Some of the items are as old as 37 years. Steps should be taken to clear the outstanding balance.

(Para 10 of report No. 61)

 

Para 28 Non-receipt of Materials against advance payment of Rs. 708.69 lacs.

As per procedure in vogue, advance payments are made to oil companies and to Railway authorities for procurement of road materials like Bitumen and for construction of Rail over Bridge respectively. During inspection of various NH Divisions it has been observed that supplies are either not received or short supplies received from the concerned parties against such advances as a result, balance amount of advance remains un-recovered/un-adjusted for years together.

Example is given below:

    1. Scrutiny of bitumen file No. 4/4 part X of NH Division Dhanabad-I revealed that 665.91 MT bitumen costing Rs. 46.52 lacs was short supplied during the period from 1995-96 to 1997-98 against advance payment. The above mentioned shortage could not be recovered from oil companies till 28.2.99

(Para 7 of report 19)

  

Para 29 Deposit Work – with Railways

The record of World Bank Project Division PW(B&R) Ambala Cantt. shows that an amount of Rs 708.69 lacs was paid to Railway authorities for construction of three Railway over Bridges as detailed below :

 

Year of payment

Amount

1993-94

11.19 lacs

1994-95

100.00 lacs

1995-96

148.50 lacs

1996-97

149.00 lacs

1998-99

200.00 lacs

1999-2000

100.00 lacs

 

Rs. 708.69 lacs

 

The estimated cost of ROB’s was revised to Rs. 960 lacs as per Ministry of Surface Transport’s letter No. 12016/87/93/N/HR/VolIII dated 11.11.97. But it is observed from the records of the Division that there is no significant progress in execution of the work. Out of three, the works of only one ROB is in progress. As it is the Deposit work for Railways and 80% payment has already been made to the Railway authorities, it is apprehended that delay in execution of work may lead to another revision of Estimates. It has been desired that the issue may be taken up with Railways and accountability be fixed accordingly.

(Para 2 of Report no. 60)

 

 Para 30 Fictitious adjustment of Materials, amounting to Rs. 108.50 lacs

As per common prudence substantiated with rules, no material should be purchased for/booked to the work unless it is required in near future. Superfluous booking and its subsequent withdrawal either to stock or by transfer to other work tantamounts to breach of financial propriety. It has been revealed from review of Inspection Reports of different NH Divisions that materials worth Rs 108.50 lacs were booked to NH Works at the fag end of the financial year.

A few instances are given below :

30.1 Scrutiny of Transfer Entry Order book of NH Division Sambalpur revealed that the expenditure of Rs. 24 lacs on works were incurred initially by the Division by Diverting fund from other woks and subsequently adjusted when funds were received for those works as detailed below :-

Item No of Adj. Register

Particulars

Debit

Credit

29 of 3/97

A sum of Rs 486000/- erroneously charge to credit of work and now withdrawn.

006/OR/91/161 Rs. 486000/-

M/R to NH 42 Rs. 486000/-

31 of 3/97

A sum of Rs 363302/- erroneously charge to credit of work and now withdrawn.

Impt. to widening surface.

006/OR/94/243 Rs.363302/-

M/R to NH 6 way Rs.363302/-

37 of 3/97

A sum of Rs 292399/- erroneously charge to credit of work and now withdrawn.

  1. 006/OR/95/130 Rs.271998/-
  2. 042/OR/94/245 Rs.16744/-
  3. 042/OR/98/077 Rs. 3657/-

292399/-

M/R to NH 42 Rs. 292399/-

54 of 3/96

A sum of Rs 398039/- erroneously charge to credit of work and now withdrawn.

  1. AA/042/OR/92/114 Rs.83763/-
  2. 042/OR/94/264 Rs.150459/-
  3. 042/OR/89/069 Rs.163817/-

398039/-

042/OR/94/25: Rs.398039/-

11 of 3/98

A sum of Rs. 360899/- being the cost of 32.13 MT bitumen

P/R to NH 6 Rs 360899/-

006/OR/97/129 Rs.360899/-

19 of 3/98

A sum of Rs. 500106/- being the cost of 44.533 MT bitumen

006/OR/97/129 Rs 500106/-

P/Rt NH 6 Rs.500106/-

(Para 1 of report No. 8)

    1. On verification of records of NH Division Solan, it is seen that material valued at Rs. 6,63,415/- (steel) was booked to the work at the fag end of the year to avoid lapse of funds whereas the said material was not required for that particular work. The material was subsequently transferred to other work/stock after the close of the year.
    2. (Para 1 of report No. 53)

    3. On verification of records of NH Division Rohtak it is observed that material worth Rs. 50.66 lacs was adjusted by transfer to other works vide TE No. 8 of 6.1.98 for Rs. 5,66,023, TE No. 1 dated 17.3.98 for Rs 12,85,067 and TE No. 2 & 3 of 4/98 for Rs 32,15,212/-. Thus keeping the material un-utilized in one work for years together and then transferring it to other work that too without requirement tantamounts to fictitious adjustment of material which needs justification.

(Para 13 of report No. 59.)

 

  

Para 31 Faulty financial and contractual Accounting worth Rs. 788.58 lacs.

It is mandatory for the contractor to execute the work as per the specification and the conditions of contract detailed in the schedule of work which forms a part of the contract. Audit has observed that there is deviation from the specifications but the works are accepted by the divisional officers without accounting for the deviation. Payment on hand receipts, splitting up of Jobs, wrong booking of Expenditure incurred on repairs of central Machines, rejection of lowest tender on enhancement of tender value without approval of Ministry of Surface transport. Non-recovery of levied compensation are some of the reasons for faulty financial and contractual accounting resulting in financial loss to Ministry of Surface Transport.

A few instances are noted as under :

    1. On going through the records/accounts of NH Division- VII Panji it is noticed that work of construction of 322 metres high level Bridge across village Chopra on NH 17- Calvale Bridge, Job no. 17/Goa/79/029 was awarded to NPCC for Rs. 235 lacs in July 1980 to be completed by July 1985. After executing the work for Rs. 134 lacs, the contract was terminated due to slow progress of work in July 1985. This contract was terminated under the clause 3(c) of the contract and balance work was awarded to contractor UPSBC for Rs. 375 lacs in 9/89 to be completed by 10/91. Though the quantum of work was reduced due to change on account of dispute regarding sinking of well piers, the contractor demanded 451 lacs as revised Estimates alongwith additional mobilization advance which was not sanctioned. As a result, the contractor did not resume the work. Subsequently this contract was terminated in 2/95 under the same clause 3(c). It is seen from the available records that recovery of compensation for delay in completion of work amounting to Rs. 23.50 lacs and Rs. 619.61 lacs are outstanding against NDCC and UPSBC Ltd.
    2. (Para 1 of report No. 16)

    3. During scrutiny of records pertaining to Express way project contract No. IX & X in respect of Express way Division- III Vadodara, it is noticed that the work of construction of Express way between Ahmedabad & Vadodara, for Rs. 26 Crores was awarded to Joint venture company i.e. M/S Continental Costruction Ltd. and its foreign counterpart M/S Belfare Beautly in two parts in 6/87 with the stipulated date of completion being 29.2.92. In addition to the inability of agency to handle the work, differences also arose between the two parties which led to winding up of Joint Venture in 4/91. Supplementary agreement was entered in 4/91 with the resident partner which agreed to take over entire contractual obligations stipulated in the original agreement subject to time limit upto 12/94 for completion of this work. Due to slow progress and abandonment of work, contract was terminated in 12/94 under clause 63 of the agreement. Thereafter it is seen that the division has not made any efforts to complete the balance work. If the work has to be carried out at present on SORs it would be amounting to more than 125 Crore to the Govt. This has resulted in loss of more than 100 crores to the Government. Division has been functioning without doing any work for the last five years.

(Para 5 of report No. 72)

31.3 During test check of records of NH Division IX Nasik it is observed that a loss of Rs. 36.10 lacs occurred to Ministry of Surface Transport due to awarding the work to an incompetent contractor in respect of Job No. AA/050/MH/92-370. The work was withdrawn after 2 ½ years because of laxity on the part of state PWD.

As per the observations of the IAP the tenders were invited at the estimated cost of Rs. 20.96 lacs. Two of the contractors having experience in the bridge works quoted Rs. 23.26 i.e. 11% above the estimated cost whereas Shri P.M. Bagul of Nasik being a fresh contractor quoted Rs 20.74 lacs, i.e. 1% below the estimated cost and his offer was accepted and work awarded to him. Shri Bagul was handed over the site on 17.1.94 with the instructions to complete the work by June 95. But the work was not started by the contractor during 2 ½ years except for providing diversion road. At the request of the contractor the department has withdrawn the work on 15.1.97 under clause 3(c) of the agreement. The blance work was awarded to Shri B.M. Gunjal another contractor in 1997-98 for Rs 54.58 lacs. All this has resulted in extra expenditure as detailed below :-

Original tender to Shri Bagul Rs 20.74 lacs

Wok executed by Shri Bagul Rs 2.26 lacs

Cost of balance work to be executed Rs 18.48 lacs

Accepted tender of Shri Gunjal Rs 54.58 lacs

Extra Expenditure involved Rs 36.10 lacs

 

Total amount recoverable from Shri Bagul has been worked to Rs. 37.74 lacs.

(i) Difference in cost of work(as per details above) Rs. 36.10 lacs

(ii) Cost of un-used cement Rs. 0.40 lacs.

(iii) Liquidated damages Rs 1.24 lacs

Rs 37.74 lacs

(Para 3 of report No. 11)

 

Para 32 Escalation charges amounting to Rs. 1980.51 lacs

Clause 10CC of the agreement of the contract provides for compensation in case of statutory increase in prices of materials, POL or labour component to be paid to the contractor have to be incorporated before hand. There escalation charges become due to the contractor subject to certain conditions. The date of completion of work within the stipulated period is the main criteria for consideration of escalation charges. The cost of work on which escalation charges are payable, shall be taken into account after deducting the cost of Extra items work executed departmentally and the cost of material issued departmentally. It should be reckoned as 85% of the cost of work after deduction of above mentioned elements. During the test check it is observed that above conditions are not being adhered to strictly resulting in higher payment of Escalation to the contractors. In a few sample cased this is to the tune of Rs. 1980.51 lacs, during 1999-2000 which is a direct financial loss to the Central Govt. (Ministry of Surface Transport).

A few examples in support of above observation are given below :

 

32.1 Scrutiny of records of NH Division Tonk(Rajasthan) revealed that the work "Re-alignment and improvement to geometrics( Bonthly By Pass) from KM 134/150 to 140/650 of Jaipur-Tonk Road of NH-12" (Job No. 012/RJ/90/108 was awarded to M/S Bhawan va Path Nirman (Bohra) & Company with stipulated date of completion of 5.12.1993. Actual date of completion of work was 30.6.95 with delay of 572 days. The final extension was granted by Addl. Secy., Govt. of Rajasthan with imposing the compensation @ 1% amounting to Rs. 25184/-. As the contractor was penalised by imposing compensation he is not entitled to receive the price excalation. The excess price excalation of Rs. 17,97,874/- was paid to the contractor out of which Rs. 9,59,526 has been recovered & balance of Rs. 8,38,348/- is still outstanding against the contractor which may be recovered form the contractor immediately.

(Para 1(1) of report No. 38)

    1. On scrutiny of records of Vasai Geak Bridge on Navi Mumbai, it is observed that the work of widening and strengthening between KM 439/00 to 497/00 of NH-8 was to be executed with the aid of World Bank loan. As per condition of the loan, the entire project is to be completed by March 2001 failing which the liability of World Bank viz payments made after March 2001 would cease. In case the project extends beyond the above period, the burden of payment would shift to Ministry of Surface Transport. The audit has noticed the slow progress in the project. The fact has already been brought to the notice of D.G.(Road) Ministry of Surface Transport.
    2. (Para-1 of report No. 45)

    3. On verification of accounts records of ADB-II Palwal it is seen that as per interim payment certificate no. 60(IPC) paid vide cheque no. 957018 dated 16.6.98 M.B. No. 3988/25 to 35 payment on account of price escalations has been made to the firm as detailed below :
    4. i) Variation of Price (Labour) 8,46,09,577.93

      ii) Variation of Price (General) 5,91,26,398.88

      iii)Variation of Price (HSD/POL) 3,60,11,691.80

      17,97,47,668.61

      It has also been observed that no documentary evidence has been found attached with the bill to prove the price escalation and their payment to the firm.

      (Para 1(C) of report No. 77)

    5. Similarly in respect of ADB project Division No PW DB & R Br. Faridabad it is noticed that as per interim payment certificate no. 65(IPC) paid vide cheque no. 911777 dated 10.6.99 M.B. No. 6358/110 to 153 payments as per details given below on account of price escalation as a result of price variation has been made to the firm

i) Variation of Price (Labour) 8,89,88,323.65

ii) Variation of Price (General) 6,21,16,194.08

iii)Variation of Price (HSD/POL) 3,81,00,289.85

18,92,04,807.58

It has also been observed that no documentary evidence has been found attached with the bill to prove the price escalation and their payment to the firm.

(Para 1 of report No. 78)

Para 33 Loss of revenue and mis-classification of revenue receipts amounting to Rs. 246.28 lacs

Govt. of India, Ministry of Surface Transport incurs expenditure on National Highway on items pertaining to Original works, other schemes and maintenance & repairs of National Highway. As such all receipts realized relating to NH work (such as sale of tenders, road cutting charges, value of empties, forfeited amount of lapsed deposits, rent from hotels, hire charges of Machinery, road side advertisements etc should be either taken as central Govt. revenue under MH-1054-other receipts or should be taken as reduction of cost of the work under 5054-capital outlay on NH . During test check of records of NH Division it is observed that a huge amount of revenues realised from the above mentioned sources have either been credited to state Govt. under "MH 0059" or kept under "8443-civil Deposits". The amount was subsequently transferred to other state works at intermittent intervals. Audit has pointed out that a total amount of Rs. 246.28 lacs involving 56 paras has been shown as mis-classified during the year 1999-2000.

A few illustrations are given below:

    1. During test check of accounts records of NH Division-II Lucknow it is seen that revenue realized from telephone Department on account of Road cutting charges from 8/96 to 5/98 has been mis-classified as "Deposit" instead of crediting to MH-1054-R&B(Central). These deposits later on have been utilised to state works which is in contravention of above instructions of Ministry of Surface Transport. The Central revenue should be credited to MH-1054 Central Head. This practice is being reported in almost all the Divisions. This needs to be discontinued immediately.
    2. (Para 7 of report No. 30)

    3. During inspection of Mech. Division Muzaffarpur it is noticed that a sum of Rs. 5,46,032/- was received from Auction of Central Machinery during 7/95 to 3/99, out of this amount, a sum of Rs. 3,01,445/- was remitted into treasury and a sum of Rs.
    4. 2,40,000 was remitted to PAO(NH) New Delhi. As per instruction of Ministry of Surface Transport Auction money after deduction of 5% for auctions commission will be remitted to PAO(NH) New Delhi. As such a sum of Rs. 5,18,730 out of Rs. 5,46,032/- should have been remitted (instead of Rs. 2,40,000/-) to PAO(NH) New Delhi. Thus short remittance of Rs. 2,78,730 has been made to PAO(NH) New Delhi. This matter has also been brought to the notice of D.G.(Road), Ministry of Surface Transport.

      (Para 1 of report No. 47)

    5. Scrutiny of records of NH Division-I Lucknow revealed that revenue realized from Telephone Department amounting to Rs. 26.91 lacs on account of road cutting charges has been credited to Deposit Head. These Deposits have been utilized to state works which is in contravention of Ministry of Surface Transport instructions.
    6. (Para 4 of report 55)

    7. Similarly, on verification of records of Mech. Division Bareilly it is observed that a sum of Rs. 55,78,005 on account of revenue realised in respect of NH works has been credited to Major Head 1054 State through Form 46. Whereas it should nave been classified in the accounts as Central receipts in forms 77 & 80. Such omissions are required to be rectified by the Division after reviewing the accounts since September 93 as no receipt is reported to be classified by the Division to Central head since that time.

(Para 1 of report No. 56)

 

 

Para 34 : Non-remittance of Toll collection receipts of Rs. 722.40 lacs.

As per notification dated 1992 of the Ministry of Surface Transport regarding fee for use of Permanent Bridges, the Divisional officer shall remit entire toll fee collection to the PAO(NH), Head Quarter through Demand Draft to enable him to credit the amount so received in relevant receipts head in his books. Thereafter the Ministry of Surface Transport sanctions/reimburses collection charges of such receipts to state concerned. But contrary to the provisions of the above mentioned procedure, the NH Divisions are not remitting the toll collection in time. In some cases the toll fee collected by the Division is not at all remitted to PAO(NH) Ministry of Surface Transport and misclassified as receipts under 8443 civil Deposits which is subsequently transferred to state Head under 0059 state receipts. As a result of internal check of the accounts of the NH Divisions it is observed that an amount of Rs. 722.40 lacs on account of toll fee collected has either been misclassified to state receipts or Deposits. This amount has not found place in the books of PAO(NH) New Delhi.

A few instances are detailed below:

    1. During inspection of records of NH Division IX Nasik, it is noticed that construction of a bridge across river Godavari in KM 415/200 of NH N.3 has since been completed for total cost of Rs. 238 lacs and was opened for traffic in September 1996. As per NH Rules, 1992 para 2(f) this bridge is subject to toll collection. But Division has not commenced Toll Collection even after two years of commissioning the bridge
    2. (Para 2 of report No. 11)

       

    3. On verification of records of NH Division, Dhanbad-II it is seen that a sum of Rs. 8.50 lacs on account of toll fee collection on Timichru Bridge has been kept in Bank. As per notification of 27th Aug 1997 issued by Ministry of Surface Transport on the subject the Supervising Officer shall remit the amount received by him on every Saturday by a demand draft to PAO(NH) Ministry of Surface Transport New Delhi.
    4. (Para. 9 of report No. 20)

       

    5. Scrutiny of records of NH Division No. 14 Nagpur revealed that toll collection is not being remitted by Division to PAO(NH) regularly. Total amount collected as Toll fee on behalf of Central Govt. has been kept in state fund which works out to Rs. 423.51 lacs. A sum of Rs. 33.78 lacs towards Toll Collection (including interest on delay payment) is also due from the Agents. This is a serious financial irregularity on the part of Division
    6. (Para 1 of report No. 32)

       

    7. On verification of records of NH Division Kaliabor, Assam it is seen that the reserved price for the year 1994-95 for Toll collection was fixed at Rs. 20 lacs whereas the total annual collection was only Rs. 15.09 lacs resulting a loss of Rs. 5 lacs during 1994-95. The reserved price of Rs 20 lacs was carried upto 1998-99. Though on the basis of the weekly traffic census(survey report) in subsequent years the reserved price qualified for an upward revision to the tune of Rs. 50 lacs. Had the reserved price been revised upward every year on the basis of Traffic census it would have fetched much higher annual return. Thus Govt. of India suffered loss due to non-revision of reserved price in the subsequent years.
    8. (Para 1 of report No. 33)

       

    9. During the scrutiny of accounts records of NH division Dhule it is observed that there has been a short remission of toll collection for Rs 16.89 lacs as per detail given below:

1- Total amount collected by way of toll fees : Rs. 9,26,98,806

2- Amount remitted to Ministry of Surface Transport : Rs. 9,10,09,338

Amount of short remittance Rs. 16,89,468

(Para 4 of report No. 80)

 

 Para 35 Misclassification of Expenditure by NH Division amounting to Rs. 78.28 lacs.

In order to project a clear and accurate picture of the Govt. account, it is the first and foremost duty of each Department to exhibit every charge of expenditure against the proper head of Account. During test check of NH Divisions, it is observed that a large number of items of Expenditure either pertaining to Minor works such as maintenance & repairs have been classified against the original works and vice versa. In certain cases the expenditure on maintenance & repairs of state machinery has been debited to NH (MOST) which is irregular and highly objectionable.

Such diversions are difficult to be found out by PAO during the pre-check of reimbursement of claims. Hence, it is desired that PWD divisions and state AG work in a more responsible manner and avoid such irregular practices.

A few instances of such misclassifications are noted below:

    1. During the scrutiny of records of NH Division – IX Nasik, it is observed that due to acceptance of tender below 17.92% of the estimated cost there was a saving of Rs. 23.57 lacs under the Job No. 003/MH/94-193. Division is utilizing this saving by debiting some maintenance & repair expenditure vide various first & final bills to this major work. Details of such expenditure is given below:
    2. MONTH Exp. in lacs

      12/97 1.86

      4/98 1.07

      5/98 2.13

      6/98 1.45

      10/98 0.81

      7.32

      (Para 4(b) of report No. 11)

    3. Scrutiny of records of NH Division Tezpur revealed that expenditure of Rs. 10.60 lacs on maintenance works FDR works and other original works were booked to Job No. 052-AS-98-807. The booking of above types of Expenditure inflated the expenditure of this original work. Diversion of fund is not permissible to and from one specific work to another work or from original work to maintenance work or vice versa.
    4. (Para 1(c) of report No. 12)

    5. On verification of records of NH Division-14 Nagpur, it is seen that an amount of Rs. 12.69 lacs relating to M & R expenditure has been debited to Major work with the following details
    6. S. No.

      Sdno/TE Month

      Amount

      Job No.

      1

      3

      3/99

      8,89,538

      98-275 or 274

      2

      SD-3

      TE-4

      3/99

      2,69,204

      98-273 or 274

      3

      Sd-7

      1,08,342

      98-521

      (Para 6 of report No. 32)

    7. During test check of record of NH Division Pen(Maharashtra) it is noticed that an amount of Rs. 6.80 lacs the work of constructions of CD works in 130/00 to 147/00. As per TE No. ABI/73 of 6/99 Expenditure was withdrawn and booked to Job No. AA/017/MH/96-219 – constructions of Major Bridge across Savitri river on PMP road KM 129/400. This may be withdrawn from the Job.

(Para 4(c) of report No. 74)

 

 

Para 36 Non – adjustment/Misclassification of hire charges of Rs. 1320.04 lacs

In order to facilitate the execution of works, the Ministry of Surface Transport lends Machines and HOT Mix Plant to intending contractors on hire charges basis. Accordingly, hire charges should be collected from the hirer from the hour on which the plant/Machinery are handed over at the work site till it is returned. Divisions are required to submit a schedule of recovery of hire charges of Central Machines with the monthly account/claims for re-imbursement of expenditure on NH. The hire charges so depicted in the monthly account are credited as Revenue Receipts under 1054 of the Central Govt. by the concerned RPAO. Test check reveals that these instructions are not being followed by some divisions. This has resulted in a loss of revenue Receipts of Rs. 1320.04 lacs.

A few instances are quoted below:

    1. During scrutiny of records of Mech., Division Lucknow it is observed that an amount of Rs. 38.88 lacs being the receipt realised on account of Hire charges of Central Machinery has been misclassified to the state Head instead of Central Head of Accounts 1054- as detailed below:
    2. TEO No.

      Date

      Amount

      IV & V

      31.10.96

      24,05,997

      I

      31.1.98

      2,83,124

      II

      31.1.98

      3,07,320

      II

      23.9.98

      4,24,390

      I

      24.10.98

      4,67,043

         

      38,87,874

      Above amount has been credited to state head of Account by A.G., U.P. as the same was not shown in re-imbursement claims received from A.G.,U.P. To credit the above amount to central head of Account a revised T.E. may be drawn in light of AG’s endorsement No. Book(Works)-I/A/C/98-99/40-41 dated 6.1.99

      (Para1 of report No. 22)

    3. Scrutiny of records of NH Division Hazaribagh revealed that the total number of 20 machines working under this Division including the three H.M.P.S at Kurso Topchanchi and Raj ganj upto 3/99 have earned revenue as hire charges amounting to Rs. 1,43,16,626.18. Out of this amount; a sum of Rs. 2,47,553.54 only has been credited to central revenue head 1054(R & B) as detailed below:
    4. Adj. No.

      Month

      Amount

      1

      3/96

      50,000

      2

      3/96

      50,000

      3

      3/97

      24,250

      2

      3/98

      1,23,30.54

         

      2,47,553.54

      Thus a huge amount of Rs. 1,40,69,072.64 (1,43,16,626.18-2,47,553.54) is still with the division and needs to be credited to MH 1054(R & B)-800 Other Receipts of Ministry of Surface Transport.

      (Para 1 of report No. 46)

    5. On verification of records of Mech. Division Bareilly, it has been noticed that hire charges from 1994-95 to 1998-99 Rs. 920.83 lacs have been received by the Division from different NH Division whose works were being executed with the help of central Machines. As per monthly progress report a sum of Rs. 32,79,294 – has been credited since 1994-95 by means of Transfer Entries from time to time. Thus a sum of Rs. 8,88,03,706/- out of above said hire charges received is still lying with the Division which requires to be remitted to PAO(NH) Ministry of Surface Transport, New Delhi.
    6. (Para 2(a) of report No. 56)

       

    7. During the course of inspection of accounts records of Mech. Division Bareilly it has been observed that hire charges amounting to Rs. 99.98 lacs due to be recovered from different NH Divisions as detailed below have not so far been received and accounted for under MH-1054

 

Name of Division

Amount in lacs

NH Division Lucknow

40.65

NH Division Sitapur

16.55

NH Division Bareilly

29.75

NH Division Moradabad

12.73

Total

99.98

(Para 2 (b) of report No. 56)

 

 Para 37 Non-Maintenance/Improper maintenance and non production of records.

The work of construction and maintenance of National Highway are entrusted to the PWD(NH) Divisions of State Govt. The expenditure incurred on this account by State Governments is subsequently charged to Ministry of Surface Transport through RPAOs(NH). As such the initial accounting records are invariably required to be maintained by PWD Divisions so as to watch and monitor the accounts of expenditure incurred and receipts realised from time to time. Test check of the records of Divisions revealed that in many cases basic accounting records are either not being maintained or being maintained improperly. There are several instances reported by the RPAOs where certain accounting records were not produced to Audit.

Non/Improper maintenance of initial records like cash Book, subsidiary cash book, contractor ledger, Register of M.Bs works Register, Receipt Book, liability Register, stock Register, T & P Register, T E Books, Road Material Accounts, Register of interest Bearing Securities, Register of Deposits, Register of Purchase, MPWA Register, log Book, tender sale Register, Tender opening Register, Agreement, Priced store ledger, Hindrance Register, Monthly account in some cases, Register of Mobilization Advances and Register of Land Acquisition Advance etc. has been pointed out by the IAP in respect of almost all the Divisions inspected during the year 1999-2000.

 

Non-Production of records is a very serious lapse and proper appropriation of Ministry of Surface Transport funds cannot be ascertained and authenticated. For this reason the Audit is unable to work out the loss caused to Ministry of Surface Transport in certain cases because of non availability of the proper registers/records.

A few examples of such irregularities are quoted below:-

Name of Division Records not maintained/produced
CW Division Ferozpur
  1. Tender Opening Register
  2. Register of Expenditure- Form 2
  3. Objection Book Register
  4. Deposit Register
  5. Inspection Report of Chief Technical Examiner, SE and Chief Engineer.
  6. Priced Store Ledger.
  7. Supply Order Book.
  8. Register of Interest bearing Securities.

(Para 10 & 11 of report No. 40)

CW Division Jalandhar Punjab

  1. Register of Agreement.
  2. Contractor Ledger
  3. Register of Form-27
  4. Fixed Charges Register
  5. Register of Chief Technical Examiner.
  6. Deposit Register
  7. Register of Purchase
  8. Supply Order Register
  9. Register of Divisional Accountant Objection Book
  10. Work Order Register

(Para 10,11 & 12 of report No. 48)

SE(MOST) Gandhi Nagar

  1. Cash Book
  2. Acquittance Register
  3. Dead Stock Register
  4. Verification of Service Books.
  5. Verification of Leave Accounts.

(Para 1,2,3 & 4 of report No. 70)

 

Para 38 Misappropriation of funds/Materials

On scrutiny of records of NH Division Cuttack it is found that Shri P.C. Samantarey JE NH Section Panikaili did not hand over the 2.100 MT Steel to his successor at the time of relinquishing his charges of the section on 20.1.93. The materials were kept under the custody of Shri Samantarey since 30.9.1985. It was confirmed by sub-divisional officer NH sub-Division PaniKaili vide his letter No- 407 dated 24.10.98 that the whereabouts of the steel could not be found. The cost of the steel had not been worked out. If the material has not been returned by Shri Samantarey, the cost of the same has to be worked out and action taken as per rule 16 of General financial Rules.

(Para 6 of report No. 61)

  

 

SPECIAL PARAS

Para 39 Use of Inferior type of Material at Zira-Talwandi-Faridkot Road KM/185-05 to 223-75.

During the checking of records of CW Division Ferozepur it has been pointed out by IAP that some inferior type of material has been used on Zira-Talwandi-Faridkot Road KM/185-05 to 223-75. The affected portion of the corridor on the above National Highway has also been inspected by Director Quality Control Cell and raised the following observations.

 

  1. That the work has not been got done as per Ministry of Surface Transport specifications. That MOST specifications from BUSC to LBM have been changed without the prior approval of SE(RW) MOST Chandigarh.
  2.  

  3. That pre-qualification of tenderers has not been done which is in violation of rules.
  4. That the work was to be carried out on composite basis rather than taking supply of Material separately and laying and consolidation of material separately.
  5.  

  6. That the samples taken out at site were not of standard quality and failed at laboratory tests.

This has resulted into excess expenditure to be incurred to the tune of Rs. 28,26,097/- for further repairing. Later on the work was rescinded & re-tendered for Rs. 87.20 lacs at the risk of the contractor i.e. M/S Momak Engineers Chandigarh. But the audit has observed that the said amount has not so far been recovered.

(Para 2 of report No. 40)

 

SPECIAL PARAS

Para 40 whereabouts of 276 Govt. Machineries are not known.

From the records of Mechanical Division Muzaffarpur it has been noticed by IAP that whereabouts of 276 central Machines could not be located. These machines were declared Beyond Economical Repair and auction thereof was sanctioned by competent authority in the year 1986. In this connection Chief Engineer(NH) Mechanical Patna vide his letter no. 1828 dated 20.10.1994 has also enquired into from all Executive Engineers of Bihar to locate the missing condemned machines so that action could be taken on auction sanctioned in 1986. But to no avail so far. This is a very serious lapse on the part of State P.W. Divisions. As such some suitable action has to be taken by the Ministry to get the depreciated value of these machines and amount to be recovered from the State Government.

(Para 2(2) of Report No. 47)

  

SPECIAL PARAS

Para 41 Construction of drainage to avoid recurring expenditure-Suggestion of IAP

As a result of scrutiny of the records of NH Division, Bahri, Bihar it was noticed that an expenditure to the tune of Rs. 3.50 to 4.00 lacs is being incurred by the Division on yearly basis for restoration of traffic in the road stretch in Champaran Bazar portion in KM 264 to KM 265 due to water logging particularly in the Monsoon period. All this is due to the fact that the level of the road is lower than the two flanks. So it was suggested to the Ministry to get deep drains constructed on both sides of the road beyond the hard shouldered part along that portion of the road to avoid re-curring expenditure under MH-"3054-Maintenance & Repairs."

The suggestion has been considered favourably by the Ministry and instructions issued to the Project Director NHAI, Jhumri Teliya, Koderma(Bihar) as per General Manager NHAI New Delhi letter No 11022/3/99/Tech/GM(WB)/130 dated 11.4.2000 for taking suitable measures in this regard.

(Para 4 of report no. 68)

 

 

Contents ] Accounts ] IA MANUAL ] OTHER PUBLICATIONS ] Search ] Accounts at A Glance ]

Up ] DIRECT PAYMENT ] [ IA Review 2000 ] NH Act ] Miscellaneous ] IA Review 2001 ]
Home ] Up ] DIRECT PAYMENT ] [ IA Review 2000 ] NH Act ] Miscellaneous ] IA Review 2001 ]
Last modified: September 11, 2000

This page is designed and maintained by  Dy.CA(A)

O/O Chief Controller of Accounts.