| |
[ Home ] [ Up ] [ Spl Audit Report ] [ Observations ] [ Issues ] [ Lighthouse Act ]
[ Contents ] [ Accounts ] [ IA MANUAL ] [ OTHER PUBLICATIONS ] [ Search ] [ Accounts at A Glance ]

- It has been observed that divisions exceed expenditure over the allocated fund for the
project and in many cases the excess is beyond 100% invariably 15% excess is allowed even
without getting the RCE approved hence cost escalation can not be controlled by RPAO.
As per para 2.10 (G) of CPWD Manual Vol.-II, the Audit Officer/Accounts
Officer has been authorised to admit expenditure in excess of sanctioned amount upto 15%
of the sanctioned amount of rupees one crore whichever is less, unless the scheme or
project has been substanitially altered. If the view of AFA-II is accepted, then the
provisions under above said para has to be got changed from the competent authority or
Controller General of Accounts. The proposed amendment to ibid rule may say that no excess
expenditure will be reimbursed by the Audit Officer/Accounts Officer unless these are got
approved by the division from the Competent Authority by presenting revised cost estimates
(anticipated excess expenditure over and above the sanctioned estimates). This exercise
should begin after the completion of ¾ work of the project.
The view that excess expenditure should be admitted by PAO if caused by
increase in cost of labour or material during the period is not tenable. It will become
difficult for PAO to identify the reasons for increase in labour cost, material cost. For
this, the new guidelines had to be made in consultation with DG(RD) & Controller
General of Accounts, on the subject. As such, we are of the view that CPWD Divisions may
be asked to obtain invariably the approval of the Competent Authority if any excess
anticipated over and above of the sanctioned estimates.
- It has been noticed that cost escalation contributed by any factor is assumed to be
leading to excess expenditure on supervision and inspection of the project, hence, by
default additional agency charges are also paid. Even though expenditure on supervision
and inspection of the project remains the same. This needs to be reviewed.
There is no specific provision in the CPWD Manual Vol. II on the
subject of payment of additional Agency Charges on revised cost estimates. As already
pointed out that it has been noticed that cost escalation contributed by any factor is
assumed to be leading to excess expenditure on supervision and inspection of the project,
hence, by default additional agency charges are also reimbursed by PAO. We are of the view
that no additional agency charges should be paid if cost escalation factor relates to
labour and material and period of execution of projects remains unchanged. If the period
of execution is changed, then agency charges have to be reimbursed on the basis of revised
cost estimates or on proportionate basis period earlier allowed and new time
of execution of projects. As Department has to expend extra on supervision and work
charged establishment etc.. IF the above view is not accepted, then fresh norms have to be
laid on the subject after consulting the concerned parties and CGA.
- Land Acquisition Estimates.
Wherever land is acquired RPAO is not provided with the details of the
budget for this purpose and details of the land to be acquired. Therefore, it is not
possible to ascertain whether right, appropriate and proper claim is being raised by State
PWD. Above details need to be provided to RPAOs to enable him to exercise proper checks.
The Para 2.1 of MOSTs letter No. NH-11029/2/87-NHIII/DI dated
3.2.1999 provides that Land Acquisition Estimates should include : minimum statutory/
obligatory charges covering the cost of publication, establishment and other legal charges
demanded by the Revenue Department in accordance with the amended LA Act in the State.
II Actual amount of compensation for land and property thereon.
III Contingencies @ 3%. This would cover the likely expenditure on
actual demarcation, measurements and other field works etc. including preparation of
working drawings.
The payment of contingencies @ 3% seems to be on very high side as
sometimes the cost of Land acquisition works out in lakhs and crores of rupees. Only a
fixed amount may be paid to PWD for taking the physical possession of the land acquired
for roads etc. The activity of possession is a limited one and it does not require much
establishment and labour etc. Land acquired amount is handed over to owners by the revenue
department of Land acquisition authority of the state. This needs change. This may be done
in consultation with D.G. Roads. (There after the expenses on development of acquired land
for road purpose should be debited to the ensuing road projects.)
No agency charges are payable to state PWD.
4. Centage charges on establishment
It has been noticed that expenditure on maintenance of National
Highways is primarily consumed by work charged establishments. There are guidelines with
respect to new projects on work charged establishment expenditure. It is prescribed that
it should not be more than 2% of the project estimate (including contingency). However, no
guideline has been prescribed for the maintenance related works.
MOST may be asked to specify the percentage of total expenditure to be
incurred on establishment attached to a particular project. This aspect may be specified
as a separate unit in the estimates itself. Divisions/PAOs may be asked to restrict the
amount to that extent. The persons/establishment of the project may also be well defined
(to be engaged) so as to avoid confusion (at a later date) alround. Divisions may also be
asked to reflect the expenditure incurred on the establishment of the project separately.
5. Agency Charges
We are of the opinion that all expenses incurred towards supervision,
vehicles, stationery & other establishment expenses be looked distinctly under the
head Agency Charges and supporting vouchers be forwarded to Regional Pay & Accounts
Officer. The claim on Agency Charges be reimbursed on actual basis or restricted to 9% of
the sanctioned estimates which ever is less. In case a particular establishment is shared
by two or more NH works/projects the admissible expenditure on each project towards agency
charges should be divided accordingly. This aspect is to be identified prior to the start
of projects (shared) and ratio of charges determined and intimated to PAO in advance.
It is pertinent to mention here that RPAO is also not informed about
various centages (other than agency charges) paid to State Government. Divisions also do
not submit the break up of the same. In the event of non-availability of details of
centages in the sanctions and non-submission of account reflecting these centages, it is
not possible to have a control over the wrong booking of the expenditure. The point raised
at Sl. No.-2 is regarding payment of additional Agency Charges on revised cost estimates.
No specific provision exists in the CPWD Manual Vol,II on the subject. As already pointed
out that it has been noticed that cost escalation contributed by any factor is assumed to
be leading to excess expenditure on supervision and inspection of the project, hence, by
default additional agency charges are also reimbursed by PAO. We are of the view that no
additional agency charges should be paid if cost escalation factor relates to labour and
material and period of execution of projects remain unchanged. If the period of execution
is changed, then agency charges have to be reimbursed on the basis of revised cost
estimates or on proportionate basis-period earlier allowed- and new time of execution of
projects. As department has to expend extra on supervision and work charged establishment
etc. If the above view is not accepted, then fresh norms have to be laid on the subject
after consulting the concerned parties and CGA. Sanctions issued by the Ministry do not
reflect the component-wise break up i.e. expenditure on material, manpower, supervision
charges, quality control etc. Hence, it is not possible to ascertain whether the project
estimates approved by the Ministry are adhered to in right spirit. O/o DG(Rd) has been
contacted time and again to get the details of various centages, however, reply is still
awaited (copy of latest reminder enclosed).
6. For the maintenance-related work on National
Highways, lump-sum provision is made for the State Govt., which, in turn, allocates the
fund to respective NH, PWDs. However, this allocation is not communicated to RPAOs. Hence,
excess expenditure incurred by Divisions could not be controlled.
7. It has been observed that new capital works are carried out by State
PWDs on contract basis. Hence, expenditure on work charged establishment should not be
there. However, estimates including work charged expenditure are approved by the Ministry
and claims are received by RPAOs. This needs to be reviewed and if need be fresh
instructions may be issued.

[ Home ] [ Up ] [ Spl Audit Report ] [ Observations ] [ Issues ] [ Lighthouse Act ]
[ Contents ] [ Accounts ] [ IA MANUAL ] [ OTHER PUBLICATIONS ] [ Search ] [ Accounts at A Glance ]
|