OFFICE OF CHIEF CONTROLLER OF ACCOUNTS MINISTRY OF SURFACE TRANSPORT GOVERNMENT OF INDIA ABOUT OFFICE ABOUT US CONTACT US OTHER LINKS |
|
SPECIAL AUDIT
Background Mumbai Port Trust owns and operates multi user and multi-cargo Marine Oil Terminal (MOT) at Jawahar Dweep (JD), Mumbai. Three MOT berths constructed in 1955 handle crude Oil and its product, transported to HPCL and BPCL refineries at Trombay, through submarine and land pipelines between JD and Pir. Pau (PP). These pipelines have been in operation since 1955 and have outlived its design Life of 20 years. Project under audit is to replace these pipelines with higher diameters including provision of new manifold at PP & JD. The project was sanctioned by the Govt. at an Estimated Cost of Rs.165.15 crores (Aug 94 prices) with a foreign exchange component of Rs.85.07 Crore vide MOSTs letter No.PD-11011/3/BPT dated 28.3.95. The estimate was based on the cost indicated by EIL in the DPR (June 1993). The project was scheduled to be completed by Dec.,97 within 34 month from March95 Initially the proposal was to replace the Old pipeline, but subsequently it was observed, as per suggestion from consultant M/s KRJ Brown, Singapore that the construction of new manifolds at JD and PP is also required to be replaced as they had also outlived their design life (Annexure I). Hence the original cost estimate (OCE) has been revised to Rs.270.08 crores (excluding IDC) in April, 98. The RCE is, thus, more by Rs.104.93 crore (63.5%) to the OCE. MBPT sanctioned the RCE on 14th July, 98 and before the approval of RCE from Govt./Ministry the MBPT awarded the contract to Hyundai Heavy Industries Ltd. Korea on 21st Jan. 99 at a cost of Rs.243 crores and the work is expected to be completed by the end of June, 2000. To fix the responsibility for time and cost for over runs, the standing committee meeting under the chairmanship of AS&FA, in connection with the Revised Cost Estimate, was held on 22.3.99. The standing committee has recommended that the persons responsible for not preparing the RCE in time, not seeking its timely approval and awarding the contract without taking the Govt. approval for the RCE needs to be identified and responsibility shall accordingly be fixed. The committee further suggested that a special audit of this project at this stage would be desirable. On the recommendation of standing committee the special audit of this project "Replacement of existing seven submarine pipeline between MOT and Jawahar Dweep and Pir Pau at Mumbai Port was conducted by Sh. K. Immanuel, PAO(NH), Sh.J.L. Ramnani, AAO and Sh. Y.N. Subedi, AAO from 13.12.99 to 22.12.99. Shri Ajay Shanker Singh, Dy. Controller of Accounts supervised the special audit from 20.12.99 to 22.12.99.
Finding of Special Audit
Under section 93(1) of MPT Act 1963 the prior sanction of the Govt. is necessary for any Revised Cost Estimate which exceeds the original cost estimate to the limit prescribed by the Govt. from time to time. Further according to section 92(1) of the MPT Act 1963 to debit the expenditure from Revenue head to Capital head of Account, the prior approval of the Govt. is necessary. However, this was also pointed out by the Financial Advisor and Chief Accounts Officer vide his letter No.FA/Awe-I-86(86) Pt-XII dt. 16.6.98 to the Secretary and Sh.D.B. Kulkarni, Project Director (Annexure II). But to no avail. The board awarded the contract to Hyundai Heavy Industries Korea on 21.1.99 without getting prior approval from the ministry for their RCE which contravenes the rules ibid. Thus the MBPT committed the liability without prior approval from the Ministry. Despite the advise of FA & CAO board decided to do so hence Secretary, MBPT is considered to be responsible for committing this blunder.
While reviewing the files furnished to audit, it was observed that all files contain only the correspondence. These files do not contain the notes portion as the project office does not maintain the notes. In the absence of which it could not be ascertained that where the files has been held up and for how much time span. The observation in audit was made purely on verifying the correspondence. Following two letters found in the file emphasised the need to enter into contact at an early date
Findings : follow the prescribed procedure. Infact letter (ii) very effectively communicates to gear-up to enter into the contract within the assured time frame which is lacking (ii). Record management is not proper.
2. Appointment of M/s Engineers India Ltd. Preparation of Detailed Project Report (DPRs) of 2 project .
A British firm M/s Scott Wilson Kirpatrick (SWK) was appointed by Asian Development Bank (ADB) in 1993 to review the reports prepared by M/s EIL on the above schemes under a Technical Assistance Scheme agreed upon between Govt. of India and A.D.B. Accordingly S.W.K. reviewed the report and approved both of them finally in 6/93. Bombay Port Trust in the Board meeting held on 9.6.93 sanctioned amount of Rs.159 Cr. for replacement of sub marine project vide TR-327 dt. 9/9/93. Cost of which was updated to 165.15 cr. and submitted to Govt. of India for approval. SWK recommended two lines of 48" diameter for crude Oil which was not accepted. However it did not object to any of the findings of EIL. SWK was appointed by ADB and it conducted its study on the behest of ADB. EILs findings were found to be useful and implemented as it is, except one addition. New manifold was suggested by the present consultant M/s KRJ Brown at Pir Pau and Jawahar Dweep. Justification given by the consultant are not in conformity with the observations of M/s EIL(Annexure I). EIL in its observations on design has taken into consideration the pressure on lines, drop of pressure in transit and pressure required at Pir Pau marifold without any replacement. It says "the new pipelines shall be connected to the existing lines at Jawahar Dweep and Pir Pau Marifold by hot tapping upstream or down-stream (as the case may be) of the valves on the existing pipelines so that the change-over does not affect the normal line operation and its operational flexibility."( Sub-para 2 of para 6.5 of report of EIL). However, the new consultant found that it is necessary to have new manifold at Pir Pau and Jawahar Dweep because of the technical reasons. The new addition has costed Rs.48.43 crores. Moreover on enquiry it was revealed that existing manifold in working perfectly and its maintenance expenditure is of routine nature which is insignificant. Though it may have lived its theoretical operational life but in practice it is in a healthy state and may continue so for may more years. This aspect has not been looked into by BPT while giving green signal to this part of the project. They have not taken pains to seek explanation from M/s KRJB on the report submitted by M/s EIL Annexure-IIIand M/s Scott Willson .
Findings : It appears they have simply agreed to the observations made by the consultant, despite knowing fully well that it is an additional component which was not suggested by M/s EIL or M/s Scott and accordingly not included in the original DPR submitted to Ministry which was approved subsequently. Despite M/s EIL & Scott recommendations BPT decided to change the manifolds at JD and Pirpau. This was stated in the point of reference for the appointment of new consultant (Annexure-IV). New manifold was decided to be erected by BPT keeping in mind the age of the existing manifold. During discussion at later stage it was also stated by the Project Director that safety feature and other parameters of the old manifold do not confirm to the present international standard. However, neither any attempt was ever made to increase the safety or change other parameters to make the existing manifold internationally acceptable nor this kind of analysis was carried out by BPT. New manifold was justified only if users beyond the manifold namely BPCL and HPCL also agree to change their pipe lines and associated facilities. After a series of meetings and discussions with them (Minutes of such meetings or discussions relevant to this context are not available) it was agreed by BPCL and HPCL that they would carry out necessary changes as desired by BPT. However, why, how and when BPT desired these changes are not explicitly mentioned. On 10th Sept., 1993 Oil Coordination Committee (OCC) confirmed the commitment of BPCL and HPCL vide its letter No.OCC/GPV/8002/816/10th Sept. 1993. It was pertinent to mention that construction of new manifold is not a decision independent of laying of pipelines by HPCL and BPCL, hence financial feasibility and Economic feasibility should have been carried out by incorporating the expenses involved in these changes. From macro point of view cost on new pipe lines of BPCL and HPCL are consequential to new manifolds. Hence the feasibility, both financial and economic are not complete and Project cost reflected in records is much less than the actual. Unfortunately this aspect has not been looked into and cost involved in construction of new manifold is reflected as direct cost to be borne by BPT only. Further, on review of the files it has been observed that the project was delayed due to its being linked to modernisation of MOT. Before the Govt.s sanction for the project namely "Replacement of 7 Submarine Pipeline connecting the marine Oil Terminal, Jawahar Dweep and Pirpau marifold at Mumbai Port" the MBPT has invited for short listing of the consultant by an advertisement dated. 13.8.94. The due date for the receipt of bids were upto15.9.94. However it was extended upto 29.9.94.
(xii) On 3/8/96 CE requested MOST for sending their approval for ranking of consultant. (xiii) On 11/9/96, CE again reminded ADB for their approval for ranking of consultant.
(xvii) On 14/11/96 Govt. sent fax conveying its approval of the ranking of consultant.
ADB Loan matter At the invitation of Govt. of India a loan apprising mission of ADB visited India from 4.12.94 to 16.12.94 to appraise the proposed "Third Port Project". Division visited the project area and held discussion with the officers of MOST and the MBPT. Govt. requested the Bank to provide a loan of $ 150 million from its ordinary capital resources to finance the project in all ports. Initially MBPT decided to go for the replacement of submarine projects from its own resources and conveyed the same to MOST, New Delhi. MOST vide their letter No.PD/11011/1/3/93 BPT dt.28.3.95 has accorded sanction of Rs.165.15 crores for the above project to be completed within 34 months i.e. by Dec. 97 but extended the time upto Dec.,99 with a request to come up with RCE by 2/98 vide MOST letter dated 28.11.97. The Financial Adviser and Chief Accounts Officer vide his letter no. CA/T/ADB/ T.P.P.(94)13155 dt. 17.8.95 informed the Secretary that the BPT is capable of meeting the entire fund requirement for the scheme which will occur in stages from its own resources and as such there appears no need for going in for ADB loan. However, if taking the scheme away from the ADB system is unavoidable, the Boards approval may be obtained in principle to raise loan from ADB loan. The Board decided to go for ADB loan and passed a resolution No.299 dt. 22.8.95 in the Boards meeting held on 22.8.95 and decided that the Chairman, MBPT should negotiate with ADB in this matter.
Director (PD) vide his letter No.PD/14014/11/93-PDF dt. 12.3.96 informed Dy. Secretary (FB) Deptt. of Economic Affairs, M/o Finance that only 2 cases of MBPT i.e. Replacement of submarine pipe lines at Bombay and Modernisation of MOT at MBPT may be taken up for ADB assistance. In letter No.PD/11011/2-BPT dt. 31.5.96 Dir (DP) informed the Chairman MBPT that Secretary (SFT) has desired that MBPT may also make comparable cash flow analysis between two sources which is more beneficial to MBPT. MBPT was reminded by MOST vide letter No.PD/14014/19/96 dated 1.7.96. MBPT vide their letter No.CE/CF/226 Dir(TPP)/4617 dt. 19.7.96 informed Director (PD), MOST that the Board vide Resolution No.202 dt. 9.7.96 has accorded approval in principle to avail of ADB funding for two projects i.e. Replacement of submarine pipelines and modernisation of MOT. MOST vide letter No.PD/14014/11/93-PDF dt. 22.1.97 confirmed the approval of Deptt. of Economic Affairs for ADB loan and asked Chairman MBPT to initiate further necessary action. ADB vide its letter dt. 29.9.97 informed the Chairman MBPT that the Board of Directors of the Bank approved the loan amounting to $ 97.8 million US $ 51.8 million for submarine pipelines project. Accordingly loan agreement was signed between G.O.I. MBPT & ADB on 25.9.98. Loan has become effecting from 6.1.99.
FINDINGS : Had the MBPT not opted for ADB Loan and met the expenditure of replacement of submarine pipelines from its internal resources the work could have been started earlier and cost overrun for this project could have been avoided. More over it is beyond comprehension that same FA & CAO advises to go ahead with internal resources and later finds that internal capital is costlier. Even if it is found that loan from ADB is cheaper all pros and cons associated with processing the loan should have been analysed. Time, manpower and expertise required to handle cases of ADB laon should have been anticipated before giving approval to it. MBPT has failed in doing so.
Bank allocation/MBPT component and total estimated cost As per ADBs estimate Name of Project Bank allocation MBPT Total estimated US $ (M) component cost US $(M) US $(M) ------------------- ------------------ -------------- --------------------
Pipelines 35.70 16.10 51.80 3. On shore pipelines 11.80 7.90 19.70 4(a) Consultancy services (US $ 7.0 M) 20.70 11.40 32.10
------- ------- -------- Total 97.80 55.30 153.10 ------- -------- --------
Project proposal Unit Original RCE Variation % Total Cost Cr. 165.15 286.60 121.45 73.53 Foreign Ex. Requirement Cr. 85.07 190.07 105.00 123.43 Project Completion Time Yr. Dec.97 June 2000 30 months Change in FE rate from Rs.31.61/US $ to Rs.42.5 US $ Details of ADB Loan Item Amount (Million US $) Submarine pipeline works 35.70 Others 25.70 Equipment 3.70 Consultancy 7.00 Interest & Commitment charges 12.00 Unallocated 13.70 Total 97.80
|
Last modified: September 12, 2000This page is designed and maintained by Dy.CA(A) O/O Chief Controller of Accounts. |